ONEOK Plans Turnaround at Bushton, Kansas, NGL Fractionator
ONEOK Field Services is planning a 7-day turnaround at its 210,000 BBL/d Bushton NGL Fractionator in Kansas beginning the third week of April. The turnaround project is valued at $1 million. Industrial Info is tracking $731 million in active ONEOK projects. ONEOK expects to see NGL volumes to be driven this year by increased drilling activity across its system. (Plant ID: 1039695)

Power
Duke Energy Belew Creek Unit 02 to Go Offline for Inspection, Repairs
Duke Energy will perform a boiler inspection as well as tube repair and cleaning on the coal-fired, 1,080-megawatt (MW) 02 Unit of the Belews Creek Power Station in North Carolina from April 15 to April 23. IIR Energy is tracking $44 million in active projects at the Belew Creek station, including a $25 million residual ash pond closure. (SERC) (Outage ID: 365572) (Plant ID: 1014219)

Refining
Valero Shuts Down Port Arthur FCCU After Failed Restart
Valero shut down the 75,000 barrel-per-day (BBL/d) catalytic cracking unit (FCCU) 1241 on Monday at its 343,000 BBL/d Port Arthur, Texas, refinery after a failed restart during the weekend. The unit was forced to shut down on March 22 due to boiler issues. Plant personnel hope to have the unit back online later today. Industrial Info is tracking $3 million in active projects at the refinery. (Plant ID: 1013116) (Outage ID: 364799)
HollyFrontier Completing Planned Maintenance at El Dorado Refinery
HollyFrontier is completing planned maintenance at its 141,000 barrel-per-day (BBL/d) El Dorado, Kansas, refinery. The work began on March 13. The Lone Crude was restarted yesterday and the 20,500 Delayed Coker was restarted today. Holly Frontier has completed catalyst changes and expects to begin restart within the next 24 to 48 hours on the 18,000 BBL/d HTU 4 Diesel Hydrotreater, 22,000 BBL/d Reformer 2 and 24,000 BBL/d HTU 2 (Heavy Naphtha) Hydrotreater, with full restart by the upcoming weekend. The El Dorado refinery’s products are marketed primarily on the eastern slope of the Rocky Mountain region, which includes eastern Colorado (including the Denver metropolitan area), eastern Wyoming and the plains states. (Plant ID: 1013966)

PetChem
CB&I Lands EPC Contract for Total Ethane Cracker in Port Arthur
CB&I has been awarded a $1.3 billion engineering, procurement and construction (EPC) contract by Total Petrochemicals & Refining USA to build an ethane cracker in Port Arthur, Texas. The cracker will have an ethylene capacity of 1 million metric tons per year. (Plant ID: 3150916)

For more information, please visit www.iirenergy.com and subscribe to the IIR blog.



Leave a Comment


comments powered by Disqus


Recomended for you...

Chemical Processing Webinar in Review: U.S. and China Remain Hotspots of Petrochemical Activity

In Industrial Info's recent Global Chemical Processing Spending Outlook webinar, Trey Hamblet, Industrial Info's vice president of research for…

United Arab Emirates Invests Heavily in Planned Power Generation, Petrochemical Projects

Power Generation and Chemical Processing projects are among the most closely watched in the United Arab Emirates (UAE), where…