Enterprise Products on Fast Track to Finish Orla Natural Gas Processing Plant

Enterprise Products Partners is on a fast track to complete construction of its Orla natural gas processing plant in Texas. Phase I, a 300 million-standard-cubic-foot-per-day (MMSCFD) train with a 40,000-barrel-per-day (BBL/d) natural gas liquids (NGL) recovery rate, is scheduled to be complete in early 2018. However, IIR Energy expects that the plant will be complete and online in late 2017. Construction of a second 300 MMSCFD, 40,000-BBL/d train is proposed to begin upon completion of Phase I. Phases 1 and 2 have a combined investment amount of $500 million. (Plant: 3259786)


NOVA Chemicals to Begin 60-day Turnaround at Corunna Olefins Unit

NOVA Chemicals is on schedule to perform planned maintenance at its 2,100 million-pound-per-year Olefins (Hot/Cold) Ethylene unit located at its Corunna plant in Ontario. The 60-day turnaround will begin August 7. (Plant: 3158223) (Outage: 160077)


NOVA Chemicals to Perform 60-day Turnaround at Ontario LDPE Unit

NOVA Chemicals is on schedule to perform planned maintenance at its 460 million-pound-per-year low density polyethylene unit located at its plant in Mooretown, Ontario. The 60-day turnaround is expected to begin August 8. (Plant: 1016795) (Outage: 357234)


Waterford Three Nuclear Unit Offline Until This Friday

The Waterford Three Nuclear Power Station unit was taken offline Monday due to stormy weather and lightning, which affected the switchyard and caused a loss of off-site power. The 1,176-megawatt unit will remain offline until Friday, July 21. (MISO) (Plant: 1013493) (Outage: 378920)


Unit 01 of Oak Grove Generating Station Offline for Repairs

Unit 01 of the Oak Grove Generating Station in Texas was offline while undergoing boiler heater plate repairs. The coal-fired, 916.8-megawatt unit will remain offline until Thursday, July 20. (ERCOT) (Plant: 1002706) (Outage: 378973)


Grand Gulf Nuclear Station Unit 01 in Mississippi Unit 01 Ramping Up After Repairs

System Energy Resources' Grand Gulf Nuclear Power Station in Mississippi was ramping up operations for Unit 01 following the completion of repairs on the ACH pump. The 1,259-megawatt (MW) unit was expected to be back to full strength by Thursday, July 20. (SERC) (Plant: 1005963) (Outage: 378918)


Marathon Restarts Reformer at Garyville Refinery

Marathon Petroleum on Tuesday restarted the 65,000-barrel-per-day (BBL/d) Reformer 212 at its 530,000-BBL/d refinery in Garyville, Louisiana. The unit was shut down for unplanned repairs on July 2. (Plant: 1018073)


For more information please visit www.iirenergy.com



Leave a Comment


comments powered by Disqus


Recomended for you...

IIR Energy BREAKERS: Natural Gas Pipeline Clears Regulatory Hurdle

IIR Energy BREAKERS: Natural Gas Pipeline Clears Regulatory Hurdle The Federal Energy Regulatory Commission (FERC) has issued a favorable…

Report: U.S. LNG Exports Boost Shipments for Expanded Panama Canal

Researched by Industrial Info Resources (Sugar Land, Texas)--The opening of the expanded Panama Canal last year has been…