IIR Energy BREAKERS: Enterprise Products on Fast Track to Finish Orla Natural Gas Processing Plant

Enterprise Products on Fast Track to Finish Orla Natural Gas Processing Plant Enterprise Products Partners is on a fast track to complete construction of its…

IIR Energy | Breakers | Nova Chemicals | Enterprise Products Partners | NGL | Waterford

Industrial Info

Wed Jul 19 2017

IIR Energy BREAKERS: Mountaineer NGL Storage Seeks Customers for NGL Caverns

Mountaineer NGL Storage Seeks Customers for NGL Caverns Mountaineer NGL Storage LLC is seeking customers for its planned 2-million-barrel natural gas liquids storage cavern near…

IIR Energy | Breakers | NGL | NatGas | Midstream

Industrial Info

Fri Jul 07 2017

IIR Energy BREAKERS: Cheniere Takes Sabine Pass LNG Train 3 Offline for Maintenance

Cheniere Takes Sabine Pass LNG Train 3 Offline for Maintenance Cheniere Energy has taken Train 3 offline for routine maintenance at its Sabine Pass liquefied…

IIR Energy | Breakers | Sabine Pass | Outage

Industrial Info

Tue Jun 27 2017

IIR Energy BREAKERS: Cheniere to Complete Sabine Pass Train 1 Maintenance

Cheniere Energy Completing Sabine Pass Train 1 Maintenance Cheniere Energy is completing a maintenance turnaround at its 4.5-million-ton-per-year Sabine Pass Train 1. The turnaround…

Breakers | IIR Energy | Tropical Storm Cindy | Outages

Industrial Info

Wed Jun 21 2017

IIR Energy BREAKERS: Power Markets See Modest Shift Back to Coal

U.S. Power Producers Shift Modestly Back to Coal from Natural Gas A shift in the relative prices of coal and natural gas has spurred…

IIR Energy | Breakers | Power Market | Cheniere | Lyondell Bassell

Industrial Info

Tue Jun 06 2017

IIR BREAKERS: Trump Withdraws U.S. from Climate Accord

IIR BREAKERS: Trump Withdraws U.S. from Climate Accord Trump Withdraws U.S. from Climate Accord President Donald Trump is withdrawing the United States from…

Trump | Climate Accord | United States | Breakers | IIR Energy

Industrial Info

Thu Jun 01 2017

IIR BREAKERS: Cheniere Starts Short Maintenance Turnaround at Sabine Pass LNG Terminal

Cheniere Starts Short Maintenance Turnaround at Sabine Pass LNG Terminal Cheniere is performing a brief maintenance turnaround at its Sabine Pass Liquefied Natural Gas (LNG)…

Breakers | IIR Energy | Power-Gen | Natural Gas | Lyondell Bassell | Lucid Energy | Cheniere | Sabine LNG | Polyethylene Maintenance

Industrial Info

Wed May 24 2017

IIR Energy Breakers

NatGas Cheniere Energy is restarting Train 1 at its two-train, 9-million-metric-ton-per-year LNG liquefaction plant in Cameron Parish, Louisiana. Train 2 is expected to come up…

Breakers | IIR Energy | Natural Gas | Refining | Petrochemicals | Power | Ethylene Outages | Planned Turnarounds | Oil Pipeline | Refinery Turnarounds | Nuclear Outages | Unplanned Coal Outage | Olefins | Planned Ethylene Cracker Turnarounds | Lyondell Bassell

Industrial Info

Tue Oct 25 2016

IIR Energy Breakers

NatGas Chevron USA Production will shut down the 200 million-standard-cubic-foot-per-day, single-train Headlee Devonian Natural Gas Processing Plant in Ector County, Texas, in November as Chevron…

IIR Energy | Breakers | Refining | Power | Refinery Maintenance | Nuclear Outage | Natural Gas Processing | Irving Oil | MISO Outages

Industrial Info

Wed Sep 28 2016

IIR Energy BREAKERS: Enterprise Products on Fast Track to Finish Orla Natural Gas Processing Plant

Enterprise Products on Fast Track to Finish Orla Natural Gas Processing Plant Enterprise Products Partners is on a fast track to complete construction of its Orla natural gas processing plant in Texas. Phase I, a 300 million-standard-cubic-foot-per-day (MMSCFD) train with a 40,000-barrel-per-day (BBL/d) natural gas liquids (NGL) recovery rate, is scheduled to be complete in early 2018. However, »

IIR Energy BREAKERS: Mountaineer NGL Storage Seeks Customers for NGL Caverns

Mountaineer NGL Storage Seeks Customers for NGL Caverns Mountaineer NGL Storage LLC is seeking customers for its planned 2-million-barrel natural gas liquids storage cavern near Clarington, Ohio. Construction has been delayed until the end of the year while Mountaineer seeks customers. Completion is scheduled for mid-2018. The storage terminal will have up to four caverns to serve producers in the »

IIR Energy BREAKERS: Cheniere Takes Sabine Pass LNG Train 3 Offline for Maintenance

Cheniere Takes Sabine Pass LNG Train 3 Offline for Maintenance Cheniere Energy has taken Train 3 offline for routine maintenance at its Sabine Pass liquefied natural gas (LNG) terminal in Cameron Parish, Louisiana. The 4.5 million-ton-per-year (650 million-standard-cubic-foot-per-day) train is expected to resume normal operations by this weekend. Cheniere has resumed production for Train 1 at Sabine Pass. Train »

IIR Energy BREAKERS: Cheniere to Complete Sabine Pass Train 1 Maintenance

Cheniere Energy Completing Sabine Pass Train 1 Maintenance Cheniere Energy is completing a maintenance turnaround at its 4.5-million-ton-per-year Sabine Pass Train 1. The turnaround began Monday. Located in Cameron Parish, Louisiana, the train is expected to be back online tomorrow. The timing of the restart may be affected by Tropical Storm Cindy. Pilots have stopped guiding ships into Sabine »

IIR Energy BREAKERS: Power Markets See Modest Shift Back to Coal

U.S. Power Producers Shift Modestly Back to Coal from Natural Gas A shift in the relative prices of coal and natural gas has spurred a modest shift in power generation away from natural gas and back toward coal (John Kemp-Reuters News). Coal costs have fallen to just $2.08 per million British thermal units compared with an average of »

IIR BREAKERS: Trump Withdraws U.S. from Climate Accord

IIR BREAKERS: Trump Withdraws U.S. from Climate Accord Trump Withdraws U.S. from Climate Accord President Donald Trump is withdrawing the United States from the 2015 Paris Climate Accord. Proponents of the withdrawal say the agreement hurts U.S. jobs and businesses, and gives overseas competitors an unfair advantage. The climate accord was reached during former President Barack Obama’ »

IIR BREAKERS: Cheniere Starts Short Maintenance Turnaround at Sabine Pass LNG Terminal

Cheniere Starts Short Maintenance Turnaround at Sabine Pass LNG Terminal Cheniere is performing a brief maintenance turnaround at its Sabine Pass Liquefied Natural Gas (LNG) Terminal in Cameron, Louisiana. The turnaround began Tuesday, and production levels should be back to normal on Thursday. Train #4 is still on track to be completed in the third quarter of this year, which »

IIR Energy Breakers

NatGas Cheniere Energy is restarting Train 1 at its two-train, 9-million-metric-ton-per-year LNG liquefaction plant in Cameron Parish, Louisiana. Train 2 is expected to come up next week following the Train 1’s restart this week. Both trains have been down since mid-September for planned maintenance and flare modifications. Volumes of gas to the plant are beginning to increase. Refining Marathon »

IIR Energy Breakers

NatGas Chevron USA Production will shut down the 200 million-standard-cubic-foot-per-day, single-train Headlee Devonian Natural Gas Processing Plant in Ector County, Texas, in November as Chevron converts it to a natural gas booster station. Canada's federal government has approved the Pacific NorthWest LNG (Liquefied Natural Gas) project in British Columbia, with 190 legally binding conditions, according to CBC News. Environment Minister »