Reliance Industries Refinery Experiences Major Fire

Reliance Industries Limited (RIL) faced a major fire incident on 210,000 b/d FCCU Unit (Design Capacity 170,000 b/d) at its 660,…

Planned Refinery Maintenance | Refinery Turnarounds | India | FCCU | Reliance Industries | Fluid Catalytic Cracking | Naphtha

Industrial Info

Thu Nov 24 2016

Key Global Refinery Maintenance Outage Updates

Petro San Felix remains on schedule to perform a 60-day planned plant-wide turnaround in early October 2016 at its 160,000 b/d Petro San…

Refinery Outage | Refinery Turnaround | Maintenance | Crude Oil | IIR Energy | FCCU | Gasoline

Industrial Info

Tue Aug 09 2016

Latest Refinery Unit Turnarounds and Maintenance Shutdowns from IIR Energy

Some recent developments: Tesoro Northwest Company is continuing with unplanned repairs on the 42,000-barrel-per-day fluid catalytic cracking unit (FCCU) at its refinery in Anacortes,…

Refining | Chemicals | FCCU | Natural Gas | Energy | China | West Coast | Southwest | Marathon | Refining Turnarounds | Refining Outages | Maintenance Turnarounds | Oil Trading | Crude Trading

Industrial Info

Thu Jul 14 2016

Reliance Industries Refinery Experiences Major Fire

Reliance Industries Limited (RIL) faced a major fire incident on 210,000 b/d FCCU Unit (Design Capacity 170,000 b/d) at its 660,000 b/d Domestic Tariff Area Refinery, India on November 24, 2016. There was no impact on production as the FCCU block was already under planned Maintenance shutdown since November 14, 2016. Major units include »

Key Global Refinery Maintenance Outage Updates

Petro San Felix remains on schedule to perform a 60-day planned plant-wide turnaround in early October 2016 at its 160,000 b/d Petro San Felix Venezuela Crude Upgrader. Units will resume activities by the end of November, 2016. Par Hawaii Refining LLC is in the process of completing a planned plant wide maintenance turnaround at its 75,000 b/ »

Latest Refinery Unit Turnarounds and Maintenance Shutdowns from IIR Energy

Some recent developments: Tesoro Northwest Company is continuing with unplanned repairs on the 42,000-barrel-per-day fluid catalytic cracking unit (FCCU) at its refinery in Anacortes, Washington, after the unit was forced to shut down due to mechanical issues. Marathon Petroleum Corporation was forced to shut down and reduce rates on several units, due to an interruption in natural gas supply »